[edit] Introduction
The construction industry is continually being challenged to deliver improvements in the outcome of projects and programmes of work. Collaboration and better integration of teams are seen as ways to achieve this.
NEC has been at the forefront of the process, creating a suite of contracts that allow all members of the supply chain to be engaged on similar terms and conditions.
[edit] Moving towards alliancing
Demand for better integration of teams continues – particularly for large, highly complex projects and programmes. In these situations, some clients have adopted a fully integrated delivery model known as an 'alliance'.
An alliance is where the client and key members of the supply chain are engaged under a single multi-party contract with shared objectives, risks and rewards. In the UK and internationally, most notably Australia, alliances have delivered better outcomes for both clients and suppliers, with increased efficiency and fewer disputes.
In 2015, the UK government advisory body Infrastructure UK published 'Improving Infrastructure Delivery: Alliancing Code of Practice'. This said there was a clear business case for using alliancing as a procurement route, with increased efficiency being delivered through behavioural and cultural change.
[edit] New NEC4 Alliance Contract (ALC)
Existing NEC contracts are bi-party arrangements onto which an alliance arrangement can be overlaid, such as by using secondary option X12. In 2016, NEC worked with the UK Infrastructure Client Group to publish Guidance on implementing alliancing using NEC3 contracts.
NEC users have requested the development of a distinct alliancing form in which all participants are engaged under a single multi-party contract. This has led to development of the new NEC4 Alliance Contract (ALC), which will initially be published in consultative form to allow industry feedback.
The basis of the contract is that all parties work together in achieving client objectives, and share in the risks and benefits of doing so.
The new ALC is therefore very different from other contracts in the NEC4 suite. However, it follows where possible the same principles and structure of other NEC4 contracts with familiar provisions, proactive management processes and terminology.
[edit] Benefits to users
The potential benefit of using the new ALC is a much deeper collaboration between all project participants, bound by common interests and reduced grounds for dispute.
The contract drives appropriate behaviours in the alliance members through:
- An emphasis on outcomes.
- Creation of a commercial model which rewards expected behaviours.
- Alignment of goals with client and suppliers.
- Use of integrated systems and processes.
- A best-for-project philosophy.
Commercial performance is measured at an alliance rather than individual party level, with reward criteria based on client's objectives. All alliance members are engaged on an open-book basis with project-specific incentive arrangements agreed at the outset.
This article was originally published here on 26 June 2017 by ICE. It was written by Matthew Garratt and Ian Heaphy, NEC4 Contract Board Members.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- Articles by ICE on Designing Buildings Wiki.
- ICE Conditions of Contract.
- NEC contracts and collaborative working.
- NEC4.
- NEC4 Design, Build and Operate Contract.
- NEC4 - legal and insurance aspects.
- NEC contract change management systems.
- NEC4 contract creates a procurement alliance arrangement for all stakeholders.
- Partnering.
- Procurement route.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.